Things are really coming together for the Trager MicroForest Project, with a significant amount of progress being made on construction last week. Both the light poles and seating were delivered and installed. The catenary lights that will be suspended from the poles will not be installed until after the tree planting so the tree planting doesn't interfere with the cable or lights.
Full Care was also able to install the benches, so now we have seating along both the interior and exterior of the walking path.
With the light poles and seating installed, not too much work is left to do before the final planting. Some additional lighting will be installed along the bottom of the retaining wall, the path will be finished with another layer of crushed stones, and some more research equipment will be installed.