The Trager MicroForest site is beginning to look quite different. Last week was one of the busiest so far, with 15 new wall pieces being delivered to the site. All 15 pieces were put into place on top of the concrete footer. Most of the remaining wall pieces are smaller, so these large pieces have completed a significant portion of the retaining wall.