Project Update

Full Care returned to the MicroForest site last week to do further work on the lighting system and central retaining wall. The space between wall pieces were mortared to bonded them together and create a smooth continues finish.

Full Care working on mortaring the wall pieces

The hardware needed to install the lighting poles has been delivered. This allowed for Full Care to dig out the holes and set up electrical infrastructure for the lighting. This week, they will begin to pour concrete for the poles.

Hole where a pole for the catenary lights will go